Daily Schedule Week of Apr 14–18, 2026
Crew Mon 4/14 Tue 4/15 Wed 4/16 Thu 4/17 Fri 4/18
Stephen
get Van, Horn, 11:30 Anielski
Wysocki AM, Grutter PM
Grutter all day. Packer route.
Wolowski 8:30 + Wysocki PM
Menards Alpine pickup AM
Tim
Wysocki — Trim doors/jambs
Wysocki — casing + cabinets
off for MRI. Maybe Grutters afternoon.
Wysocki — wall caps + handrail
Wysocki — barn door install
Jordan
Grutter demo
Grutter demo cont.
Grutter framing
Grutter, Wolowski
Grutter
Josh
Wysocki, 11:30 Anielski
Wysocki all day
Wysocki
Wysocki + Wolowski 8:30
Wysocki finish
Brodie
Wysocki
Wysocki
Off
Wolowski
Off (Brodie Mon/Tue/Thu only)
Levi
Eikenhout pickup AM
Bringing dump trailer to Wysocki's AM
Repcolite Plainfield — stain pickup
Hauling / returns
Off

Schedule Editor Press Enter to parse
Schedule · Mon Apr 16
Parsed assignments

Pickups & Returns
  • PICKUP
    Eikenhout — screen for Wittmer
    Devon will deliver. Stephen will remove this note once it's confirmed completed.
  • PICKUP
    Menards Alpine — 2x4s for Grutter addition
  • PICKUP
    Repcolite Plainfield — can of stain for Wysocki trim
  • RETURN
    Eikenhout — return PVC trim boards (Horn job, leftover)
  • PICKUP
    Menards Alpine — hardware for Grutter deck ledger

Weather-Deferred Soon, on a clear day once the ground is thawed
  • Horn — pole barn cleanup
    yard cleanup, return scrap · needs dry ground
    next clear day: Thu Apr 23
  • Wysocki — exterior caulking
    needs >50°F sustained temp
    next clear day: Thu Apr 23
  • Grutter — finish grade backfill at addition
    ground still partially frozen
    next clear day: Fri Apr 24
  • Marlene Ploeg — deck staining
    needs 3 consecutive dry days · ground is thawed in May
    next clear day: May 2

QBO Sync 7 jobs awaiting reconciliation in QuickBooks
Marlene Ploeg — fence replacement
Completed field · invoice pending QBO
NEEDS INVOICE
Quenzer — barn shingles
Completed in QBO · confirm payment
COMPLETE
Horn — front door + backsplash
Field complete · final invoice not sent
NEEDS INVOICE
Gull Lake Ministries — building 3 HVAC trim
Invoiced · awaiting payment
INVOICED
need to invoice final payment schedule — Grutter addition
Milestone 2 complete · 3 payments remaining
SCHEDULE NEEDED

Repeat Clients
Marlene Ploeg
5 projects · $24,800 lifetime
Long time repeat client. Currently: basement cabinet face frame + LVP flooring. Last visit Sep 2025. Needs final payment schedule.
Gull Lake Ministries
6 projects · 3 buildings active
Steve Kortlever (maintenance director). Recurring commercial. ~4 weeks across multiple buildings. Current phase: building 3 interior trim.
Kevin & Rachel Quenzer
4 projects · long time repeat clients
Last job: barn shingles, May 2025. Completed in QBO. Likely to call for spring exterior work.
This dashboard is a custom mockup built by BYS — BraceYourself Solutions · See the full pitch → · Book a call
Job Details