Daily Schedule
Week of Apr 14–18, 2026
| Crew | Mon 4/14 | Tue 4/15 | Wed 4/16 | Thu 4/17 | Fri 4/18 |
|---|---|---|---|---|---|
| Stephen |
get Van, Horn, 11:30 Anielski
|
Wysocki AM, Grutter PM
|
Grutter all day. Packer route.
|
Wolowski 8:30 + Wysocki PM
|
Menards Alpine pickup AM
|
| Tim |
Wysocki — Trim doors/jambs
|
Wysocki — casing + cabinets
|
off for MRI. Maybe Grutters afternoon.
|
Wysocki — wall caps + handrail
|
Wysocki — barn door install
|
| Jordan |
Grutter demo
|
Grutter demo cont.
|
Grutter framing
|
Grutter, Wolowski
|
Grutter
|
| Josh |
Wysocki, 11:30 Anielski
|
Wysocki all day
|
Wysocki
|
Wysocki + Wolowski 8:30
|
Wysocki finish
|
| Brodie |
Wysocki
|
Wysocki
|
Off
|
Wolowski
|
Off (Brodie Mon/Tue/Thu only)
|
| Levi |
Eikenhout pickup AM
|
Bringing dump trailer to Wysocki's AM
|
Repcolite Plainfield — stain pickup
|
Hauling / returns
|
Off
|
Schedule Editor
Press Enter to parse
Parsed assignments
Pickups & Returns
-
PICKUP
Eikenhout — screen for WittmerDevon will deliver. Stephen will remove this note once it's confirmed completed.
-
PICKUP
Menards Alpine — 2x4s for Grutter addition
-
PICKUP
Repcolite Plainfield — can of stain for Wysocki trim
-
RETURN
Eikenhout — return PVC trim boards (Horn job, leftover)
-
PICKUP
Menards Alpine — hardware for Grutter deck ledger
Weather-Deferred
Soon, on a clear day once the ground is thawed
-
Horn — pole barn cleanupyard cleanup, return scrap · needs dry ground
-
Wysocki — exterior caulkingneeds >50°F sustained temp
-
Grutter — finish grade backfill at additionground still partially frozen
-
Marlene Ploeg — deck stainingneeds 3 consecutive dry days · ground is thawed in May
QBO Sync
7 jobs awaiting reconciliation in QuickBooks
Marlene Ploeg — fence replacement
Completed field · invoice pending QBO
Quenzer — barn shingles
Completed in QBO · confirm payment
Horn — front door + backsplash
Field complete · final invoice not sent
Gull Lake Ministries — building 3 HVAC trim
Invoiced · awaiting payment
need to invoice final payment schedule — Grutter addition
Milestone 2 complete · 3 payments remaining
Repeat Clients
Marlene Ploeg
5 projects · $24,800 lifetime
Long time repeat client. Currently: basement cabinet face frame + LVP flooring.
Last visit Sep 2025. Needs final payment schedule.
Gull Lake Ministries
6 projects · 3 buildings active
Steve Kortlever (maintenance director). Recurring commercial. ~4 weeks across multiple buildings.
Current phase: building 3 interior trim.
Kevin & Rachel Quenzer
4 projects · long time repeat clients
Last job: barn shingles, May 2025. Completed in QBO. Likely to call for spring exterior work.